MPP Solar PIP-MS 1-5KVA Guide d'installation Page 15

  • Télécharger
  • Ajouter à mon manuel
  • Imprimer
  • Page
    / 16
  • Table des matières
  • MARQUE LIVRES
  • Noté. / 5. Basé sur avis des utilisateurs
Vue de la page 14
15
Step 4: Switch on all AC breakers of Line wires in AC input. Its better to have all inverters connect to utility at
the same time. If not, it will display fault 82 in following-order inverters. However, these inverters will
automatically restart. If detecting AC connection, they will work normally.
LCD display in Master unit
LCD display in Slave unit
Step 5: If there is no more fault alarm, the parallel system is completely installed.
Step 6: Please switch on all breakers of Line wires in load side. This system will start to provide power to the
load.
Support three-phase equipment
Step 1: Check the following requirements before commissioning:
Correct wire connection
Ensure all breakers in Line wires of load side are open and each Neutral wires of each unit are connected
together.
Step 2: Turn on all units and configure LCD program 28 as P1, P2 and P3 sequentially. And then shut down all
units.
NOTE: It’s necessary to turn off switch when setting LCD program. Otherwise, the setting can not be
programmed.
Step 3: Turn on all units sequentially.
LCD display in L1-phase unit LCD display in L2-phase unit
LCD display in L3-phase unit
Step 4: Switch on all AC breakers of Line wires in AC input. If AC connection is detected and three phases are
matched with unit setting, they will work normally. Otherwise, the AC icon will flash and they will not work
in line mode.
LCD display in L1-phase unit
LCD display in L2-phase unit
LCD display in L3-phase unit
Step 5: If there is no more fault alarm, the system to support 3-phase equipment is completely installed.
Step 6: Please switch on all breakers of Line wires in load side. This system will start to provide power to the
load.
Note 1: To avoid overload occurring, before turning on breakers in load side, its better to have whole system
in operation first.
Note 2: Transfer time for this operation exists. Power interruption may happen to critical devices, which cannot
bear transfer time.
Vue de la page 14
1 2 ... 10 11 12 13 14 15 16

Commentaires sur ces manuels

Pas de commentaire